Project Management Professional (version 2023)

Question 49 of 200
A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for installation and testing. The carrier
sends an email to the project manager stating that one appointment is delayed for 2 days.
What does the project manager need to do now?