Project Management Professional (version 2023)

Question 43 of 200
A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the
measurement was accurate.
What should the project manager do next?