Project Management Professional (version 2023)

Question 37 of 200
A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is
concerned about the project's performance and wants to take action in advance to ensure the project succeeds.
What should the project manager do?