Project Management Professional (version 2023)

Question 176 of 200
A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is identified regarding an indirect tax regulation that is being changed by the government in the next 6
months. This risk will have a significant impact on the project outcomes.
What should the project manager do next?