Project Management Professional (version 2023)

Question 152 of 200
During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from
implementing the project. The project manager realizes that this could be a high risk for the project.
Which action should the project manager take?