Project Management Professional (version 2023)

Question 15 of 200
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach. This is a critical project for the organization and, in the middle of the project, the project manager noticed
that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?