Project Management Professional (version 2023)

Question 149 of 200
A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed a delay in contracting. After communicating with the contract department, the project manager
found the contract team is prioritizing other contracting jobs because they are not part of the project team.
What should the project manager do first in this situation?