Project Management Professional (version 2023)

Question 148 of 200
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the
opinions of the product owner seriously and mostly relies on the project manager's opinion.
What should the project manager do?