Project Management Professional (version 2023)

Question 145 of 200
An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started working at the company. In the first meeting with the project manager, the director demands a
weekly project status report.
What should the project manager do?