Project Management Professional (version 2023)

Question 120 of 200
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified the project manager that there is a capacity issue for the team
doing the installation.
What should the project manager have done to prevent this situation from happening?