Project Management Professional (version 2023)

Question 119 of 200
In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a specific machine available in the market. When the machine reached its destination country, it was
blocked by customs authorities who restricted the import of this machine model.
What should the project manager have done to prevent this from happening?