Project Management Professional (version 2023)

Question 106 of 200
A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team. This has caused delivery delays
and, ultimately, the failure to complete the project.
What is the root cause of this issue?