The sponsor of an agile project checked the information radiators and expressed his concern about the slow progress of the project when compared to a similar project executed by the same team using waterfall approach about a year back. The scrum master invites the sponsor to join one of the scrum meetings to know more about the project. Which of the following scrum events would be the most beneficial for the sponsor to attend as per scrum best practices?