PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 89 of 120
Ryan is an agile project leader who is working on a software development project with his team. During each iteration planning meeting, one of the project stakeholders suggests some new features to add in the product. However, the new features are not aligned with the proposed goal of the project, agreed at the beginning by all the project stakeholders. Which of the following is the most appropriate action taken by Ryan in this situation?