Question 74 of 120
While working on a hybrid project, an agile practitioner is responsible to perform the duties of both the project scrum master and provide project performance reports periodically to the senior management. The project sponsor suggests the agile practitioner that track the velocity of each team member individually instead of tracking the team velocity as a whole in order to monitor the progress of the project. What would the agile practitioner do as per agile best practices?