Question 69 of 120
A new program manager has been appointed for the ongoing agile project. He has used traditional project management practices for tracking the actual project performance against the planned baselines, and so requests for regular updates on the overall progress of a high priority agile project. The program manager can neither spend more than five minutes on the updates of the project nor able to micromanage the team’s work. Which of the following is the most appropriate response to the request of the program manager, assuming that the project is using weekly sprints?