PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 62 of 120
An agile team has been working on a project for about the last two months and have just completed only the fifth iteration out of ten. As shown in the release burndown chart, for the last three iterations, the curve that represents the actual completed work is approx 40 points above the straight descending line of the projected work. If the team’s velocity is 20, which of the following is correct for the given details?