PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 58 of 120
On the completion of the first three iterations, an agile team determined that 344 story points are required to complete the remaining project. The average team velocity in the first three iterations was 50 story points. What will be the number of iterations required for the team to complete the project?