In the first iteration of the agile team, daily standup meeting lasts over 30 minutes. In the retrospective meeting, the team decided to use the Shu-Ha-Ri model in order to reduce the duration of daily standup meetings and keep it more focused. During the second iteration, the team was able to focus on the three basic questions, ensure that daily standup meetings complete within 15 minutes, and follow the agenda. Which of the following level of the Shu-Ha-Ri model the team had completed at the end of the second iteration?