A business sponsor is trying to do some negotiations with a potential contractor for the web application upgrade project. Both the contractor and sponsor have worked together in the past on the stable requirements project, and they have great trust in each other. The current contract includes the volatile requirements that subject to change on a weekly basis. Which of the following type of contract would be most appropriate for both the parties for this project?