PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 115 of 120
Richard is an agile coach and his eXtreme Programming team is working on a development project. To be ready for any situation, Richard has set to view the end result of the project from every angle. So, the team anticipates the failure of the project and moves back to revisit the plan to find the reasons for failure.
Which of the following project management strategy have the team used for this?