PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 109 of 120
John is an agile coach handling a software development project. The stakeholder has sent an email request to share the copy of the project management plan. How should John respond to the request when he knows that the stakeholder is not even familiar with agile?