PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 107 of 120
A scrum team that has been working on an agile project, is arguing over the story points in the sprint meeting planning. The product owner is pushing the team to complete 170 story points of user stories in the next sprint whereas the average velocity of the development team is 150 story points per sprint. Who will make the final decision to fix the number of story points to be completed in a sprint?