PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 105 of 120
In an iteration planning meeting, a team member states that it is difficult to estimate the actual work needed to complete a task because of the involvement of new technology that the team is not familiar with. Also, in case of failure of the approach, this technology can result in potential risk to the project. What should the team do to determine this unknown impact?