PMI-ACP Preparation Exam Mocktest1 - Whizlabs

Question 102 of 120
Agile team members who have worked together on a few projects in the past are working on a new project. They are using story points for the estimation of the level of effort needed to complete the user stories on the new project. Which of the following is the most likely approach the team should use to estimate the first use story?