Question 10 of 120
You are appointed as an Agile practitioner to guide the team to adhere the process. One of your team member is insisting that the product owner has to write the acceptance test cases for all the stories which are included in current release. The current release is having six 2 weeks long iteration. Now, since 3 months is not a long period he suggests, it would be better if PO writes them in one go so that team can do better estimation and planning. What would you do in such scenario?